Difference between revisions of "Re-skinning"
From EUTC Wiki
m (better formating) |
|||
(One intermediate revision by the same user not shown) | |||
Line 16: | Line 16: | ||
# Pile as much weight as possible evenly over the plywood. | # Pile as much weight as possible evenly over the plywood. | ||
# Leave over night. | # Leave over night. | ||
+ | {{ Add more }} |
Latest revision as of 17:36, 13 October 2009
- Rip up old hardboard
- Pull out all the nails that didn't come out with the hardboard
- Check that you've really pulled out all the nails
- No really, check again...
- Sweep up all the muck and junk that you've created and throw it out
- Walk over each of the floorboards and check for cracks, splits and other damage
- Pull out split or cracked boards and replace with plywood/reinforce subsided boards
- Get 25 4'by8' sheets of 3.2mm hardboard
- Lay an 18mm 4'x8' plywood board on the floor
- Lay down a sheet of hardboard on the plywood.
- Make sure it's square and not hanging over any edge.
- Mop the hardboard sheet with water. Don't saturate it, but get it consistantly damp.
- Lay another sheet of hardboard on top of the first board.
- Repeat 10-13 for all the hardboard
- Cap top of hardboard with a second 4'x8' 18mm plywood sheet
- Pile as much weight as possible evenly over the plywood.
- Leave over night.
Please add more detail | |
---|---|
This article requires more information when you get a chance. |